November 3, 2015- Homeland MDP Line 1 Stage 1

Alabbasi has received notification of award for the $14.3 Million Homeland MDP Line 1 Stage 1 Project from the Riverside County Flood Control and Water Conservation District. As a part of this contract, Alabbasi will excavate and export nearly 500,000 Cubic Yards (CY) of soil (roughly 36,000 truckloads). Alabbasi will also construct over 4,000 Lineal Feet (LF) of 72″- 96″ Reinforced Concrete Pipe (RCP), 1,900 LF Double 10′x7′ Precast Reinforced Concrete Box (PRCB), and 2,500 LF of 12′x6′ PRCB. These precast joints will be shipped in 8′ lengths and will weigh in at 41,000 pounds a joint.

This project will represent the third project by Alabbasi to be constructed as a part of the Homeland/ Romoland Master Drainage Plan. The previous 2 phases of this project were also awarded to Alabbasi. Upon completion, Alabbasi will have moved over 2 million cubic yards of earth (exporting 1.8 million cubic yards) constructed nearly 9 miles of RCP, PRCB, RCB, Concrete Lined Trapezoidal Channel and Earthen Channel. Collectively, these projects will serve as the backbone flood control infrastructure for all future developments in the Green Valley, Homeland/ Romoland Regions. Alabbasi looks forward to another successful project in partnership with Riverside County Flood Control.

Construction is anticipated to commence during the first quarter of 2016 and should be complete by the first quarter of 2017/

October 16, 2015- Ninth Street Sewer Replacement

Alabbasi has received notification of award for the $1.9 Million Ninth Street Sewer Replacement Project from the City of Riverside. The project will replaced 8,400 LF of aged sewer lines with new 8″ and 12″ PVC sewer lines and will replace 126 residential service lines. The project is expected to commence January 2016 and should be complete by September 2016.

August 31, 2015- Low Water Crossing Replace at Avenue D and Wilson Creek

Alabbasi has received notification of award for the $1.7 Million Low Water Crossing Replacement at 13th Street and Wilson Creek from the City of Yucaipa. The project consists of constructing a triple- 19.5′ wide x 13.5′ tall Reinforced Concrete Box at the roadway crossing along with 200 lineal feet of Open Box Channel. The project will also rehabilitate D street and add new storm drain facilities. Construction is expected to commence October 2015 and continue to April 2016.

August 31, 2015- Low Water Crossing Replacement at 13th Street and Wilson Creek

Alabbasi has received notification of award for the $1.9 Million Low Water Crossing Replacement at 13th Street and Wilson Creek from the City of Yucaipa. The project consists of constructing a triple- 22′ wide x 13.5′ tall Reinforced Concrete Box at the roadway crossing along with 200 lineal feet of Open Box Channel. The project will also rehabilitate 13th street and add new storm drain facilities. Construction is expected to commence October 2015 and continue to April 2016.

February 25, 2015- Southwest Riverside MDP Line G Stage 2, Line G1 and F1 Storm Drain Project

Alabbasi has received notification of award for the $4.1 Million Southwest Riverside MDP Line G Stage 2, Line G1 and F1 Storm Drain Project from the City of Riverside. The project features 2,700 LF of 60″- 90″ RCP Storm Drain Pipe with cuts up to 25′ along the Historic Victoria Avenue and heavily traveled Van Buren Boulevard. As a part of this project, Alabbasi will also rehabilitate local surrounding streets consisting of 500,000 SF of Coldmilling and 10,500 tons of Asphalt Paving. Construction is expected to commence July 2015 and to be complete by December 2015.